Water Main Installation Along Main Street in Grasonville Expected to Begin in November

Queen Anne’s County Sanitary District is preparing for a water main installation project along Main Street in Grasonville, with construction tentatively scheduled to begin Nov. 1, 2026.

The project will install a new water main in the eastbound lane of Main Street, beginning near the U.S. Route 50/301 Exit 42 area and extending east to the Chester River Beach Road overpass.

Construction will be completed using a combination of directional drilling and conventional open-trench installation. The section from approximately Exit 41 to Exit 43A near Queenstown Bank will be directionally drilled. The remainder of the project will use conventional open-trench construction. Work is expected to begin with the directional drilling portion of the project.

Construction is scheduled Monday through Friday, excluding major holidays. Directional drilling operations are expected to take place from 7 a.m. to 4 p.m., while open-trench work will take place from 7 a.m. to 5 p.m.

Motorists can expect some traffic disruptions and are encouraged to allow additional travel time when work is taking place. Traffic impacts will vary depending on the location but travelers can anticipate partial lane closures with flagging operations. We will contact homeowners and businesses along the eastbound lane directly if there will be an impact to accessing their driveway. Drivers are asked to use caution, reduce speeds and follow all posted signs and directions when traveling through the work zone.

The project is expected to continue through 2027, with the current contract establishing a completion date in mid-October 2027.

Properties located along the new water main route will not be required to connect to the public water system solely because the new main is being installed. Existing properties may continue using their wells unless a well completely fails. Connection requirements may apply to new development.

Queen Anne’s County will provide additional information as construction progresses, particularly when work moves into new areas or when significant traffic impacts are anticipated.

Project updates will be shared through Queen Anne’s County Government’s website and social media channels. For questions or concerns, contact the Department of Public Works, Sanitary District 410-643-3535.